For Electrical, MEP and Civil Contractors · P6 Scheduling & Delay Support · Nationwide

The GC has a scheduler. The owner has a reviewer. Now you have one too.

CPM Pros reviews the GC's Primavera P6 schedule from the trade contractor's side, so electrical, mechanical, plumbing, fire protection and civil contractors get realistic durations, access dates and crew sizes before the dates become a commitment. We also build the schedule your subcontract requires, update it with each pay application, and document delays with fragnets and time impact analyses (a fragnet is a short piece of schedule inserted to show a delay's effect) while there is still time to be paid for them. No P6 license needed.

Who we support: electrical contractors, mechanical, plumbing and fire protection contractors, controls contractors, and civil and site contractors working under a general contractor, anywhere in the US. Most send us the GC's schedule PDF or their contract. You get a written quote with a firm price and delivery date, typically within 3 business days.

Send the GC Schedule PDF · Get a Quote or call 206-719-2053

The Situations We Solve for Trade Contractors

Put it in the schedule,
in writing

Your contract requires it

The GC requires a CPM schedule and you don't own P6

We build your scope schedule in our P6 environment and deliver the XER and PDF the GC's scheduler expects, coordinated with the project schedule.

Written quote in 3 business days Your schedule, built →
Being delayed

The GC or another trade is delaying you

A fragnet or TIA tied to the project schedule turns "they slowed us down" into a time extension request or delay claim the GC can pass through to the owner, before the money is gone.

Written quote in 3 business days Document the delay →
Flow-down LDs

Liquidated damages are flowing down to you

Your defense is a contemporaneous schedule record showing your work on time or excusably delayed. We build and maintain that record from day one.

Written quote in 3 business days Keep the time you are owed →
Pay application support

Your contract ties schedule updates to pay apps

If your contract requires a schedule update with each pay app, we keep it current and aligned to your billing, so payment disputes start from your record, not the GC's memory.

Every billing cycle Monthly updates →
Before you accept the dates

Get the GC's schedule corrected before you sign off on it

Sequence, durations, and logic in the GC's P6 file determine your float, access dates, and delay exposure. We review it from your side and arm you to get it fixed.

Written quote in 3 business days GC schedule review →
Submittal rejected

Your schedule submittal came back with comments

We correct the file, respond comment-by-comment, and prepare the resubmittal in 3–5 business days.

3–5 days Schedule rescue →

For Electrical, MEP and Civil Contractors

When the GC's schedule
squeezes your scope

Before you accept the dates

Review the GC's schedule from your side

Your durations, access dates and logic ties checked against how your crews actually install, with a written list of what to correct before the dates become your commitment.

GC schedule review →
Compressed durations

The GC keeps shortening your activities

Each update compared to the last and to the baseline, with every cut duration logged and the crew size it now requires shown in writing.

Constructive acceleration →
Out of sequence

Predecessor trades are late and you're working around them

Out-of-sequence work, trade stacking and lost access documented against the GC's schedule, with a fragnet or TIA when the time is supportable.

Document the delay →
Civil and site work

Your site isn't ready and the weather won't cooperate

Late site access, weather days beyond the contract allowance, and permit windows recorded month by month, so lost time is documented when it happens.

Civil scheduling →
Equipment and submittals

Your gear drives the job and the schedule shows one bar

Switchgear, panels, air handlers and chillers modeled as submittal, approval, fabrication and delivery, with the dates your vendors actually quoted.

Long-lead equipment →
End of the job

Everyone ahead of you was late and your finish date didn't move

Startup, testing and commissioning squeezed into whatever time is left. We show what the trades ahead of you consumed and what your work actually needs.

Document the delay →

The same skills we use in delay disputes.

CPM Pros also works as the scheduling expert in construction delay disputes: reading XER files, reconstructing critical paths across years of updates, and testifying in arbitration and litigation. The same XER analysis goes into reviewing your GC's schedule and building your delay documentation.

Questions Contractors Ask

Can you review the GC's schedule for us before we accept our dates?

Yes. We read the GC's Primavera P6 file or PDF, check your activities, durations, access dates and logic ties, and give you a written list of what misrepresents your scope, so you can object in writing before the dates become your commitment.

The GC keeps compressing our durations. What should we do?

Document it update by update. We compare each GC update to the last one and to the baseline, log every shortened duration and changed tie that affects your scope, and show what crew size or overtime the new durations require. That record supports a written objection now, and an acceleration or disruption claim later if it comes to that.

We were pushed out of sequence. Can that support a time extension?

Sometimes. Out-of-sequence work does not automatically delay the critical path, so the analysis has to show whether it did. We build the fragnet or time impact analysis against the GC's schedule and tell you plainly whether the time is supportable before you submit the request.

The GC wants us to hold the date without a time extension. Can you show that is acceleration?

Often, yes. Constructive acceleration rests on a documented pattern: an excusable delay, timely written notice and a request for more time, a direction to hold the original date, and the added crews or overtime it took. We tie your notices, the GC's responses and each schedule update together so the cost of holding the date has a record behind it. See how constructive acceleration is documented.

Can you prepare a time impact analysis for a subcontractor on a hospital or data center job?

Yes. We insert a fragnet for the change or delay into the GC's current Primavera P6 update, recalculate, and show the effect on your milestones and the completion date, with a narrative the GC and the owner's reviewer can check step by step. On hospital work the phasing, infection control and inspection steps often drive the answer, so we model them explicitly.

I don't own Primavera P6. Is that a problem?

No. Most of the contractors we support don't. We build and maintain everything in our P6 environment and deliver the XER, PDF, and narrative. You never buy the software.

Can LDs really flow down to me?

Often, yes. Many subcontracts pass the GC's delay exposure down to you. Your protection is contemporaneous CPM documentation showing your work on time or excusably delayed. That record is what we build.

When should I document a delay: now or when the job ends?

Now. Time extensions requested late, or never formally requested, are routinely denied or waived. A fragnet built while the delay is happening is evidence; a story told at closeout is an argument.

What does it cost?

Scheduling is professional hourly work scoped per deliverable from your contract or the GC schedule PDF. You get a written quote with a firm number and delivery date, typically within 3 business days. Per-project, no long-term contract.

Will you talk to the GC's scheduler for me?

Yes. Scheduler-to-scheduler coordination is often the fastest way to get your scope shown correctly in the GC's file.

Send the GC schedule PDF. Get a firm number.

Send your contract or the GC's schedule PDF. Written quote with a firm number and delivery date, typically within 3 business days. Talk to the scheduler, not a salesperson.

Get a Written Quote

or call 206-719-2053