Forensic Scheduling

Time Impact Analysis

TIA is contract-mandated, widely used, and often misapplied. It works prospectively for EOT requests and change orders. Stretched into retrospective forensic use, it accumulates serious problems.

8 min read Forensic Scheduling

Time Impact Analysis (TIA) is one of the most commonly specified delay analysis methods in construction contracts, and one of the most commonly misapplied. The contract says the contractor must submit a TIA with every delay claim or change order request. The contractor does so, usually as a forward-looking exercise to support a request for extension of time (EOT). Years later, when the project is finished and the parties are in dispute, someone decides to use TIA retrospectively to quantify the total delay impact. That retrospective use is where TIA gets into trouble.

Understanding why requires looking at what TIA is designed to do, how AACE RP 29R-03 classifies it, and why the forensic community has increasingly cautioned against stretching it past its prospective purpose.

A Quick Orientation Within AACE RP 29R-03

TIA lives in the modeled side of the AACE taxonomy. In prospective use, it is not a formal MIP under the retrospective forensic framework, but it is the method most contracts contemplate when they specify time impact analysis for change orders or EOT requests. In retrospective use, TIA maps most closely to MIP 3.7 (Modeled / Additive / Multiple Base), where delay fragnets are inserted into the contemporaneous schedule updates that were current at the time of each delay.

The distinction between prospective TIA and retrospective TIA matters because the information available to the analyst is fundamentally different, and the defensibility of the result is correspondingly different.

What the Method Does

TIA measures the impact of a specific delay event by inserting a representation of the delay (a "fragnet" of activities with logical ties to the existing schedule) into the project schedule at or near the time the delay occurred, recalculating the CPM network, and comparing the projected completion date before and after the insertion. The difference is the time impact of the event.

In prospective use, TIA is typically applied to:

The schedule used for the analysis is the most recent contemporaneous update, and the fragnet represents the delay as understood at that point in time.

In retrospective use, the analyst applies the same technique but with the benefit of hindsight: each delay event is inserted into the contemporaneous update current at the time the delay actually occurred, and the results are aggregated across the project.

The Procedure

For a single prospective TIA:

  1. Identify the delay event and gather supporting facts (cause, duration, responsible party).
  2. Select the contemporaneous schedule update that was current when the delay occurred or is expected to occur.
  3. Construct a fragnet that represents the delay's activities with appropriate logic ties to the existing schedule.
  4. Insert the fragnet into the schedule, maintaining the original logic except where the delay explicitly modifies it.
  5. Recalculate the CPM network.
  6. Compare the projected completion date before and after the insertion. The difference is the time impact.
  7. Document assumptions about fragnet durations, logic ties, and concurrency treatment.

For retrospective multi-event TIA (MIP 3.7), repeat the process for each delay event using the contemporaneous update current at each event's date, and aggregate.

When to Use It

TIA is well-suited for:

When used prospectively, on a well-maintained schedule, for a single clearly-defined event, TIA is a clean and widely-accepted technique.

The Problem With Retrospective TIA

The forensic community has grown increasingly skeptical of retrospective TIA, and the reasons are worth understanding.

Livengood and others in the forensic community have argued that retrospective TIA should generally be replaced by windows-based or observational methods that better respect the contemporaneous record of what actually happened.

Caveats Worth Respecting

Even for prospective use, TIA requires discipline:

Where It Sits in the Bigger Picture

TIA is best understood as a prospective or near-contemporaneous tool. Used that way, inside the project's own rhythm of updates and change orders, it serves its purpose well. Stretched into retrospective forensic use, it accumulates problems that windows-based methods avoid. The practitioner's takeaway is to use TIA for what it was designed for, specify it clearly in contracts, and consider other AACE MIPs when the question is what actually happened on a completed project rather than what is likely to happen going forward.

The contract may require TIA. The dispute may benefit from something else. Understanding the difference is what separates a scheduler from a forensic analyst.


References

This content is for informational purposes only and does not constitute project-specific consulting advice. Please contact info@cpmpros.com for project-specific services. © 2024 CPM Pros. All rights reserved. Reproduction or distribution without permission is prohibited.
Related Resources